Default class 1 div 1

im bidding on a sewage lift station project and i have a question about the project. in the drawings the engineer has a 2" pipe leaving the we well which is class 1 div 1 (methane). the 2" pipe goes to a classified junction box any where from 3' to 15' away from the wet well. there is no seal off between the wet well and the junction box. there is another 2" pipe leaving the classified box that does have a seal off.
the owner wants to beable to disconnect and replace the sensors that are terminated in the box without being messedup in a sealoff. my question is is this leagle by code?

HCECalaska is offline   Reply With Quote
Join Contractor Talk

Join the #1 Electrician Forum Today - It's Totally Free!

ElectricianTalk.com - Are you a Professional Electrical Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for electricians to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your specialty is you'll find that ElectricianTalk.com is a great community to join. Best of all it's totally free!

Join ElectricianTalk.com - Click Here JOIN FOR FREE


Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ElectricianTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!
Old 03-27-2007, 11:02 PM   #2
Senior Member
 
Join Date: Jan 2007
Location: Michigan
Posts: 265
Default

They're always engineered that way around here. I have done quite a few.
We seal before entering the control cabinet. but don't seal between the j-box and wet well so they can readily change pumps and floats.
Every one of ours has passed.

And I have never put in an explosion proof junction box even when spec'd and never been dinged. The last engineer put it in the drawings to cover his behind. Our inspectors understand the need for timely maintenance and are satisfied when we seal the raceway before entering the controller.

We use a standard JIC hinged 3R box, usually with a term strip


Last edited by faber307; 03-27-2007 at 11:09 PM.
faber307 is offline   Reply With Quote
Old 03-27-2007, 11:04 PM   #3
Senior Member
 
Join Date: Mar 2007
Posts: 190
Default

we have done several classified jobs for the oil industry up here, but that is all MCHL cableing.
HCECalaska is offline   Reply With Quote
Old 03-27-2007, 11:06 PM   #4
Senior Member
 
Join Date: Jan 2007
Location: Michigan
Posts: 265
Default

Not familiar with that cable, what is it?

MI cable perhaps?
faber307 is offline   Reply With Quote
Old 03-27-2007, 11:09 PM   #5
Senior Member
 
Join Date: Mar 2007
Posts: 190
Default

it reminds me of a mix between ocal and mc cable. its essential an mc cable rated for classifed areas. it makes some very nice installations if you do it right, and really beats standard grc installations for cost and labor.
HCECalaska is offline   Reply With Quote
Old 03-27-2007, 11:10 PM   #6
Senior Member
 
Join Date: Jan 2007
Location: Michigan
Posts: 265
Default

I bitched when MC started taking over emt. But adapted slowly.
Now they're taking away my RIGID!

Oh dear............
faber307 is offline   Reply With Quote
Old 03-28-2007, 08:30 AM   #7
Senior Member
 
Join Date: Mar 2007
Location: New jersey
Posts: 182
Default

Thats terminated with a crouse hinds CGFJ = CGB with lead instead of rubber grommet The cables been around a long time used it offshore and in plants I remember a brand name like Corflex about 1/8 pvc outer then 1/4 aluminum sheath, stranded conductors ,three solid ground wires,plastic seperators,wrapped in plastic like MC.Is this the same stuff?
Louieb is offline   Reply With Quote
Old 03-28-2007, 10:39 AM   #8
Senior Member
 
Join Date: Mar 2007
Posts: 190
Default

no, this cable terminates with TMC for non hazardous areas and TMCX connectors for hazardous locations. and it realy is an MC cable with a rubberized sheath. it tranes nicly and it can be ordered with litteraly any quantity and type of conductor inside it. including fiber and beleden types.
HCECalaska is offline   Reply With Quote
Old 03-28-2007, 03:12 PM   #9
Senior Member
 
Join Date: Mar 2007
Location: New jersey
Posts: 182
Default

sounds pretty expensive ,just curious of what the temp limitations are!and are those connectors Crouse hinds or something else! My customers freak on Romex prices......Ah to be a "petrochemical animal again" or better known As'The Brotherhood of Oil Field Trash'and proud of it!Too fat to be running against the wind socks and climbing fences to hear "all clear"
Louieb is offline   Reply With Quote
Old 03-28-2007, 04:46 PM   #10
Senior Member
 
Join Date: Mar 2007
Posts: 190
Default

okanite lists the opeating temp from -40c to 90c compared to a grc classified install its is cheaper. connectors are expensire though TMC are in the $25range and the TMCX are $54.

HCECalaska is offline   Reply With Quote
Reply

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Class II Division I??? gilbequick NEC Code Forum 10 11-21-2008 09:14 PM
UK: Class III appliances Brad Ford UK Electrical Forum 2 10-06-2008 05:20 PM
class 1, div2 sparky970 NEC Code Forum 1 08-31-2008 06:52 AM
Next class is Motors JBIRD Site Help and Suggestions 0 05-19-2008 09:54 PM
Touch tests on class 2 equpment JOHNO123 General Electrical Discussion 5 07-13-2007 04:24 AM

Top of Page | View New Posts

All times are GMT -4. The time now is 02:50 PM.


Electrician Talk © 2006 - 2010 The Building Network

Search Engine Optimization by vBSEO 3.6.0 RC 2