Default Kohler Generator PM ?

Looking through the specs of a job I'm bidding, it says the following regarding a new Gen Set:

"Beginning at Substantial Completion, provide 12 months' full maintenance by skilled employees of manufacture's designated service organization. Include quarterly exercising to check for proper starting, load transfer, and running under load. Include routine preventative maintenance as recommended by manufacture and adjusting as required for proper operation. Provide parts and supplies same as those used in the manufacture and installation of original equipment."

In a different section, it states a factory trained tech needs to perform start up. How would you bid this? 3 additional quarters should satisfy this requirement, correct?

knowshorts is offline   Reply With Quote
Join Contractor Talk

Join the #1 Electrician Forum Today - It's Totally Free!

ElectricianTalk.com - Are you a Professional Electrical Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for electricians to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your specialty is you'll find that ElectricianTalk.com is a great community to join. Best of all it's totally free!

Join ElectricianTalk.com - Click Here JOIN FOR FREE


Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ElectricianTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!
Old 04-23-2012, 07:57 PM   #2
Senior Member
 
Service Call's Avatar
 
Join Date: Jul 2011
Location: Daytona Beach
Posts: 572
Default

I'd think of maybe taking the generator manufactors course and including that and the required time and material as per the proposal. If anyone lowballs the job it's cause they didn't read the specs. Good catch.

Service Call is online now   Reply With Quote
Old 04-23-2012, 08:08 PM   #3
Senior Member
 
Join Date: Dec 2010
Location: Twin Cities
Posts: 9,895
Default

Quote:
Originally Posted by knowshorts View Post
Looking through the specs of a job I'm bidding, it says the following regarding a new Gen Set:

"Beginning at Substantial Completion, provide 12 months' full maintenance by skilled employees of manufacture's designated service organization. Include quarterly exercising to check for proper starting, load transfer, and running under load. Include routine preventative maintenance as recommended by manufacture and adjusting as required for proper operation. Provide parts and supplies same as those used in the manufacture and installation of original equipment."

In a different section, it states a factory trained tech needs to perform start up. How would you bid this? 3 additional quarters should satisfy this requirement, correct?

Find an authorized dealer in your area and sub that portion out to them.
Chris1971 is online now   Reply With Quote
Old 04-24-2012, 12:45 PM   #4
Anti Political
 
Join Date: May 2007
Location: The land of no concealed carry
Posts: 1,746
Default

When we bid / order these, the usually give us an option for this service from the dealer / distributor. Another popular one is a five year warranty / service agreement.
mdfriday is online now   Reply With Quote
Old 04-24-2012, 01:23 PM   #5
Senior Member
 
Join Date: Jan 2009
Location: SoCal
Posts: 3,827
Default

I just got the information back from my supply house. The price includes a 12 month maintenance contract. I get to delete a line item. Commercial 3 phase generators are expensive.
knowshorts is offline   Reply With Quote
Reply

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Kohler vs Generac captkirk General Electrical Discussion 82 Yesterday 07:07 AM
Kohler generator ???? Elephante General Electrical Discussion 11 01-24-2012 09:51 PM
kohler gen donselec General Electrical Discussion 4 11-17-2011 07:40 AM
I'll never buy a Kohler generator again.... jwjrw General Electrical Discussion 41 10-03-2011 01:09 PM
Generator Transfer Panel Kohler petro123 NEC Code Forum 2 03-27-2011 10:53 AM

Top of Page | View New Posts

All times are GMT -4. The time now is 06:33 PM.


Electrician Talk © 2006 - 2010 The Building Network

Search Engine Optimization by vBSEO 3.6.0 RC 2