Question Instal subpanel in second structure

Hi,
I am running PVC conduit from Main panel in the house to a subpanel in separate structure about 25 feet away from the main house. The second structure will be used for office. Now I know I can't use more the 4x 90 angles of conduit, but general contractor requested to put the subpanel in area I would had to use 5 angles. I am wondering if I could use main circuit breaker disconnect on outside of the main house and then run raceway to the the subpanel, so I would eliminate use of 2 90 degree angles in a raceway.
I draw a picture so anyone could give me better idea how to do it.
Thank you.
Sincerely,
Martin

martinkulik is offline   Reply With Quote
Join Contractor Talk

Join the #1 Electrician Forum Today - It's Totally Free!

ElectricianTalk.com - Are you a Professional Electrical Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for electricians to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your specialty is you'll find that ElectricianTalk.com is a great community to join. Best of all it's totally free!

Join ElectricianTalk.com - Click Here JOIN FOR FREE


Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ElectricianTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!
Old 05-07-2009, 09:44 AM   #2
Registered Member
 
Join Date: Nov 2007
Posts: 2,575
Default

Turn your disco into a weatherproof pullbox. Turn the last 90 into a disco. That's only 2 90's in the pull.

LawnGuyLandSparky is offline   Reply With Quote
Old 05-07-2009, 10:18 AM   #3
Electrical Contractor
 
Buck Parrish's Avatar
 
Join Date: May 2009
Location: Indiana & Mostly NC for now
Posts: 178
Default

Martin, Just use direct burial cable. No conduit required. Why break your back if you don't have to?
Buck Parrish is offline   Reply With Quote
Old 05-07-2009, 02:36 PM   #4
Senior Member
 
Join Date: Sep 2007
Location: Maryland
Posts: 325
Default

You could also use an LB at the new panel. The removable cover allows the access. Could you not come into the back of the first panel?
Jim Port is offline   Reply With Quote
Old 05-07-2009, 03:00 PM   #5
Junior Member
 
Join Date: Jan 2009
Location: Suisun City, Ca
Posts: 21
Default

Thank you for your quick answers. So you can use weatherproof pull box in main feeder for the subpanel, because the line will continue without making a brake right?
martinkulik is offline   Reply With Quote
Old 05-07-2009, 03:07 PM   #6
Junior Member
 
Join Date: Jan 2009
Location: Suisun City, Ca
Posts: 21
Default

Thank you again. You said I could use direct burial. I thought about it, but then partially it would have to be in the conduit where is going to against outside structure. I wanted to use #8 Stranded copper THHN because it would be easier to pull it through the conduit. Now if I change it to direct burial cable that size it would be really hard to pull it through the conduit even though it will be probably only 10 feet.
martinkulik is offline   Reply With Quote
Old 05-08-2009, 03:05 AM   #7
Senior Member
 
erics37's Avatar
 
Join Date: May 2009
Location: Depoe Bay, Oregon
Posts: 9,942
Default

Quote:
Originally Posted by martinkulik View Post
Thank you again. You said I could use direct burial. I thought about it, but then partially it would have to be in the conduit where is going to against outside structure. I wanted to use #8 Stranded copper THHN because it would be easier to pull it through the conduit. Now if I change it to direct burial cable that size it would be really hard to pull it through the conduit even though it will be probably only 10 feet.
Direct burial wouldn't need a conduit if put in a trench the proper depth and sleeved for protection where it comes out of the ground. It would be more prone to damage and would be much more difficult to replace for future expansion, so I would say conduit and individual conductors is the way to go.

From your picture, you could do away with the disconnect on the main building and use an LB to get out of the wall. It would also allow your conduit to sit closer to the wall for support straps without having a weird gooseneck thing going on. Same deal at the subpanel end. It would make it easier to penetrate the wall to the interior, and it would eliminate some 90s.
__________________
- Eric
erics37 is offline   Reply With Quote
Old 05-08-2009, 09:16 AM   #8
Senior Member
 
Join Date: May 2009
Location: The Silver State
Posts: 105
Default

Quote:
Originally Posted by erics37 View Post
Direct burial wouldn't need a conduit if put in a trench the proper depth and sleeved for protection where it comes out of the ground. It would be more prone to damage and would be much more difficult to replace for future expansion, so I would say conduit and individual conductors is the way to go.

From your picture, you could do away with the disconnect on the main building and use an LB to get out of the wall. It would also allow your conduit to sit closer to the wall for support straps without having a weird gooseneck thing going on. Same deal at the subpanel end. It would make it easier to penetrate the wall to the interior, and it would eliminate some 90s.
Yep, I would use LBs on both structures. Then you could put the new panel inside anywhere you wanted.
NevadaBoy is offline   Reply With Quote
Old 06-05-2009, 06:31 PM   #9
Senior Member
 
Join Date: Mar 2009
Location: Illinois
Posts: 685
Default

yea definitely LB's. make sure you pound a ground rod too if they adopted the 08 code
running dummy is offline   Reply With Quote
Old 06-05-2009, 11:14 PM   #10
Moderator
 
Join Date: Jan 2007
Location: NY State
Posts: 7,520
Default

Quote:
Originally Posted by running dummy View Post
make sure you pound a ground rod too if they adopted the 08 code
What does it have to do with '08? A ground rod was always required at a detached structure with a feeder.
__________________
Time flies when you're goin' fast.
Speedy Petey is online now   Reply With Quote
Old 06-18-2009, 10:27 AM   #11
976-EVIL
 
mcclary's electrical's Avatar
 
Join Date: Feb 2009
Location: State of Euphoria
Posts: 13,408
Default

not if less than two circuits
mcclary's electrical is offline   Reply With Quote
Old 06-18-2009, 12:57 PM   #12
Moderator
 
Join Date: Jan 2007
Location: NY State
Posts: 7,520
Default

Quote:
Originally Posted by mcclary's electrical View Post
not if less than two circuits
That is why I mentioned a feeder, as opposed to a MWBC.
__________________
Time flies when you're goin' fast.
Speedy Petey is online now   Reply With Quote
Old 06-18-2009, 02:27 PM   #13
Senior Member
 
Join Date: Sep 2007
Location: Phoenix, AZ
Posts: 5,393
Default

Quote:
Martin, Just use direct burial cable. No conduit required. Why break your back if you don't have to?
Worst.....advice.....ever.

Wiring needs protection and sometimes it needs to be replaced.

And....break your back? You still have to dig. How hard is it to pull wire in properly installed conduit.

It's no more difficult to install conduit and wire.
220/221 is offline   Reply With Quote
Old 06-18-2009, 03:16 PM   #14
Electrical Savant
 
lectricboy's Avatar
 
Join Date: Mar 2009
Location: Kentucky
Posts: 478
Default

Quote:
Originally Posted by Buck Parrish View Post
Martin, Just use direct burial cable. No conduit required. Why break your back if you don't have to?

I know direct burial cable is approved for it's use. But in my opinion whenever you bury cable in the ground, you are asking for trouble. I have seen direct buried cable fail too many times (everything from rocks to moles to tree roots). I would stay with the conduit, you can always repull if something goes wrong.
lectricboy is offline   Reply With Quote
Old 06-18-2009, 07:58 PM   #15
Senior Member
 
Join Date: Sep 2007
Location: Phoenix, AZ
Posts: 5,393
Default

Quote:
I know direct burial cable is approved for it's use. But in my opinion whenever you bury cable in the ground, you are asking for trouble.
Best....advice.....ever.
220/221 is offline   Reply With Quote
Old 06-18-2009, 08:43 PM   #16
child please.....
 
NolaTigaBait's Avatar
 
Join Date: Oct 2008
Location: Hack City, USA aka New Orleans
Posts: 5,267
Default

never understood why people use uf when you could just run pvc
NolaTigaBait is offline   Reply With Quote
Old 11-11-2009, 12:20 PM   #17
Senior Member
 
sparks134's Avatar
 
Join Date: Jan 2009
Location: Pittsburgh, PA
Posts: 1,118
Default

yeah! just run rigid conduit, just have to trench 6" then!!!
__________________
Its not just a job, it's a career!!!
sparks134 is offline   Reply With Quote
Old 11-12-2009, 06:20 AM   #18
Member
 
Join Date: Nov 2009
Location: Chicago/Suburbs
Posts: 51
Default

Quote:
Originally Posted by lectricboy View Post
I would stay with the conduit, you can always repull if something goes wrong.
Not Always.
RMatthis is offline   Reply With Quote
Old 11-12-2009, 06:47 AM   #19
Senior Member
 
Join Date: Apr 2009
Location: NASA
Posts: 7,521
Default

Quote:
Originally Posted by mcclary's electrical View Post
not if less than two circuits
One circuit no grounding electrodes

Two or more circuits must have grounding electrodes.

Bob Badger is offline   Reply With Quote
Reply

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Garage subpanel k2x NEC Code Forum 12 10-02-2008 11:55 AM
60 amp subpanel nmackintosh General Electrical Discussion 53 05-12-2008 10:21 PM
? subpanel from 3pH to 1pH 120 123weld General Electrical Discussion 4 05-09-2008 05:39 AM
ceiling fan instal issue mikpowl General Electrical Discussion 15 09-17-2007 12:18 AM
SO CORD can it be used on structure? glenn easterly General Electrical Discussion 15 04-07-2007 10:20 PM