03-20-2011, 09:42 PM
|
#1
|
|
Resi Service Electrician
Join Date: Sep 2008
Location: California
Posts: 1,257
|
Sacramento County Service Ground/Bond
I'm new to Sacramento, CA (mostly worked in the S.F. Bay Area) and I am doing a couple services next week. Anyone know the local ground/bond methods?
In the bay area they want water/gas/rod, but it looks like Sac locally only wants water/rod. The service I am changing out has an existing ufer (accessible) and incoming water, both with individual ground runs. This looks to be fine, but I'm not finding any solid info until I talk to an inspector tomorrow, just trying to get a head start.
__________________
"Understand one thing every one has a place in this trade, and no matter what your skill set I doubt you know it all." brian john
Last edited by electrictim510; 03-20-2011 at 09:43 PM.
Reason: forgot to add CA
|
|
|
Join the #1 Electrician Forum Today - It's Totally Free!
ElectricianTalk.com - Are you a Professional Electrical Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for electricians to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your specialty is you'll find that ElectricianTalk.com is a great community to join. Best of all it's totally free!
Join ElectricianTalk.com - Click Here

|
Warning: The topics covered on this site include activities in which there exists the potential for serious injury
or death. ElectricianTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!
03-20-2011, 09:45 PM
|
#2
|
|
Senior Member
Join Date: May 2009
Location: Depoe Bay, Oregon
Posts: 9,925
|
Quote:
Originally Posted by electrictim510
In the bay area they want water/gas/rod...
|
They want gas pipe as a grounding electrode?
That's an NEC violation and a bad idea to boot
__________________
- Eric
|
|
|
03-20-2011, 09:51 PM
|
#3
|
|
PES
Join Date: Feb 2011
Location: NY
Posts: 1,350
|
Quote:
|
Originally Posted by erics37
They want gas pipe as a grounding electrode?
That's an NEC violation and a bad idea to boot 
|
They probably want it bonded!!
__________________
Sal
P.E.S
|
|
|
|
The Following User Says Thank You to Salvatoreg02 For This Useful Post:
|
|
03-20-2011, 09:53 PM
|
#4
|
|
Resi Service Electrician
Join Date: Sep 2008
Location: California
Posts: 1,257
|
Quote:
Originally Posted by erics37
They want gas pipe as a grounding electrode?
That's an NEC violation and a bad idea to boot 
|
They want the gas bonded in the Bay Area, Weird I know, but thats what they ask for. Usually we run a ground to the nearest water and then use a jumper at the water heater to catch hot and gas off of the cold.
__________________
"Understand one thing every one has a place in this trade, and no matter what your skill set I doubt you know it all." brian john
|
|
|
03-21-2011, 07:20 PM
|
#5
|
|
Resi Service Electrician
Join Date: Sep 2008
Location: California
Posts: 1,257
|
Well I found out they basically want it the same as the Bay Area except they want a #4 to the ufer regardless of if it is a 100 or 200 amp service.
__________________
"Understand one thing every one has a place in this trade, and no matter what your skill set I doubt you know it all." brian john
|
|
|
03-21-2011, 08:46 PM
|
#6
|
|
Senior Member
Join Date: May 2009
Location: Depoe Bay, Oregon
Posts: 9,925
|
Quote:
Originally Posted by electrictim510
They want the gas bonded in the Bay Area, Weird I know, but thats what they ask for. Usually we run a ground to the nearest water and then use a jumper at the water heater to catch hot and gas off of the cold.
|
Okay that makes more sense. Gas pipe usually needs to be bonded anyway, but often the EGC for whatever equipment is hooked up to it will suffice.
Quote:
Originally Posted by electrictim510
Well I found out they basically want it the same as the Bay Area except they want a #4 to the ufer regardless of if it is a 100 or 200 amp service.
|
I think #4 is the max required size for a GEC to a CCE.
__________________
- Eric
|
|
|
03-21-2011, 11:28 PM
|
#7
|
|
Senior Member
Join Date: Apr 2007
Location: Alaska/Nevada
Posts: 1,351
|
Quote:
Originally Posted by electrictim510
I'm new to Sacramento, CA (mostly worked in the S.F. Bay Area) and I am doing a couple services next week. Anyone know the local ground/bond methods?
In the bay area they want water/ gas/rod, but it looks like Sac locally only wants water/rod. The service I am changing out has an existing ufer (accessible) and incoming water, both with individual ground runs. This looks to be fine, but I'm not finding any solid info until I talk to an inspector tomorrow, just trying to get a head start. 
|
I'm wanting to hear about the gas? Never heard of anything like that other than a code violation!
Edit - not a putdown...curious as to what their logic is.....
__________________
Don't let fear be your guide!
Last edited by Rockyd; 03-21-2011 at 11:32 PM.
|
|
|
03-21-2011, 11:49 PM
|
#8
|
|
Heavily Armed Member
Join Date: Sep 2010
Location: Fascistchusetts
Posts: 29,498
|
Quote:
Originally Posted by electrictim510
I'm new to Sacramento, CA (mostly worked in the S.F. Bay Area) and I am doing a couple services next week. Anyone know the local ground/bond methods?
In the bay area they want water/gas/rod, but it looks like Sac locally only wants water/rod. The service I am changing out has an existing ufer (accessible) and incoming water, both with individual ground runs. This looks to be fine, but I'm not finding any solid info until I talk to an inspector tomorrow, just trying to get a head start. 
|
2011NEC
250.104 Bonding of Piping Systems and Exposed Structural Steel.
(B) Other Metal Piping.
If installed in, or attached to, a
building or structure, a metal piping system(s), including
gas piping, that is likely to become energized shall be
bonded to the service equipment enclosure; the grounded
conductor at the service; the grounding electrode conductor,
if of sufficient size; or to one or more grounding electrodes
used. The bonding conductor(s) or jumper(s) shall be
sized in accordance with 250.122, using the rating of the
circuit that is likely to energize the piping system(s). The
equipment grounding conductor for the circuit that is likely
to energize the piping shall be permitted to serve as the
bonding means. The points of attachment of the bonding
jumper(s) shall be accessible.
Informational Note No. 1: Bonding all piping and metal
air ducts within the premises will provide additional safety.
Informational Note No. 2: Additional information for gas
piping systems can be found in Section 7.13 of NFPA 54-
2009, National Fuel Gas Code.
Last edited by HARRY304E; 03-21-2011 at 11:52 PM.
|
|
|
03-22-2011, 12:10 AM
|
#9
|
|
Resi Service Electrician
Join Date: Sep 2008
Location: California
Posts: 1,257
|
I was just wondering what the local jurisdiction wanted because from city to city out here they require different bonding requirements.
__________________
"Understand one thing every one has a place in this trade, and no matter what your skill set I doubt you know it all." brian john
|
|
|
03-22-2011, 12:20 AM
|
#10
|
|
Master Plumber
Join Date: Aug 2007
Location: In your attic.
Posts: 8,107
|
Quote:
Originally Posted by electrictim510
They want the gas bonded in the Bay Area, Weird I know, but thats what they ask for. Usually we run a ground to the nearest water and then use a jumper at the water heater to catch hot and gas off of the cold.
|
Which I see it as assinine... The gas pipe is bonded at every appliance that has a cord
~Matt
__________________
Poor planning on your part does not constitute an emergency on my part.
Advertising space available. Inquire within.
|
|
|
03-22-2011, 01:21 AM
|
#11
|
|
Senior Member
Join Date: Apr 2007
Location: Alaska/Nevada
Posts: 1,351
|
Quote:
Originally Posted by TOOL_5150
Which I see it as assinine... The gas pipe is bonded at every appliance that has a cord
~Matt
|
Matt,
What code cycle are they using that they think it is okay to bond to the gas line? The reason I'm asking is the the paths of the 05, o8, and 11 are trying to move people of the industry away from using gas as an electrode.
Going all the way back to the 05 " Changes to the NEC 2005" book by Mike Holt, here is his commentary on the subject of 250.52(B)(1)
- (B) Electrodes Not Permitted.
- (1) Underground Metal Gas piping system.Underground metal gas piping systems and structures cannot be used as a grounding electrode.
(FPN)sEE 250.104(B) for the bonding requirements for gas piping.
Author's comment (Mike Holt) According to 250.104(B) metal gas piping that is likely to become energized must be bonded to the servicew equipment enclosure, the grounded (neutral) servide conductor, or hee grounding electrode conductor or grounding electrode conductor where the grounding electrode conductor is of sufficient size [250.104(B). The equipment grounding (bonding) conductor for the circuit that may energize the piping can serve as the bonding means. So effectively, this means that no no action is actually required by the electrical installer!
Let me tell you what 2008 has -
(B) Not Permitted for Use as Grounding Electrodes.
The folowing systems and materials shall not not be used as grounding electrodes:
(1) Metal underground gas piping systems
(2) Aluminum
(FPN) See 250.104(B) for bonding requirements of gas piping.
In the 2011, at 250.104(B) there is an Informational note No.2 Additional information for gas piping systems can be found in Section 7.13 of NFPA 54-2009 National Fuel Gas Code.
So I see even the NEC is working hard to stop the dangerous practice of mixxing gas and electric.Makes me wonder where California thinks they're headed legislatively, so that inspectors can go forward, rather than backwards in the industry!  
__________________
Don't let fear be your guide!
|
|
|
03-22-2011, 01:48 AM
|
#12
|
|
Master Plumber
Join Date: Aug 2007
Location: In your attic.
Posts: 8,107
|
Quote:
Originally Posted by Rockyd
Matt,
What code cycle are they using that they think it is okay to bond to the gas line? The reason I'm asking is the the paths of the 05, o8, and 11 are trying to move people of the industry away from using gas as an electrode.
Going all the way back to the 05 " Changes to the NEC 2005" book by Mike Holt, here is his commentary on the subject of 250.52(B)(1)
- (B) Electrodes Not Permitted.
- (1) Underground Metal Gas piping system.Underground metal gas piping systems and structures cannot be used as a grounding electrode.
(FPN)sEE 250.104(B) for the bonding requirements for gas piping.
Author's comment (Mike Holt) According to 250.104(B) metal gas piping that is likely to become energized must be bonded to the servicew equipment enclosure, the grounded (neutral) servide conductor, or hee grounding electrode conductor or grounding electrode conductor where the grounding electrode conductor is of sufficient size [250.104(B). The equipment grounding (bonding) conductor for the circuit that may energize the piping can serve as the bonding means. So effectively, this means that no no action is actually required by the electrical installer!
Let me tell you what 2008 has -
(B) Not Permitted for Use as Grounding Electrodes.
The folowing systems and materials shall not not be used as grounding electrodes:
(1) Metal underground gas piping systems
(2) Aluminum
(FPN) See 250.104(B) for bonding requirements of gas piping.
In the 2011, at 250.104(B) there is an Informational note No.2 Additional information for gas piping systems can be found in Section 7.13 of NFPA 54-2009 National Fuel Gas Code.
So I see even the NEC is working hard to stop the dangerous practice of mixxing gas and electric.Makes me wonder where California thinks they're headed legislatively, so that inspectors can go forward, rather than backwards in the industry!   
|
You got me wrong - we dont / cant use it as an electrode, BUT we do bond it... usually at the W/H Cold, hot and gas [not directly connected to the GES]. SF requires everything bonded through the GES. From panel, to rod, to gas and ending at water.
~Matt
__________________
Poor planning on your part does not constitute an emergency on my part.
Advertising space available. Inquire within.
|
|
|
03-22-2011, 01:54 AM
|
#13
|
|
Senior Member
Join Date: Apr 2007
Location: Alaska/Nevada
Posts: 1,351
|
Quote:
Originally Posted by TOOL_5150
You got me wrong - we dont / cant use it as an electrode, BUT we do bond it... usually at the W/H Cold, hot and gas [not directly connected to the GES]. SF requires everything bonded through the GES. From panel, to rod, to gas and ending at water.
~Matt
|
It's cool. Just curious as to how other places interpret things. Here in Alaska, if it has a gound wire going to it with the cord, romex, flex, then that covers the "likely to be energized part". Thanks for the information.
Edit - We have to pull ground wire everywhere in pipe in Anchorage, we go "over the top" on that end. Then again our ground moves a lot up here because of frost, earthquakes, etc. so it's not such a bad thing.
__________________
Don't let fear be your guide!
Last edited by Rockyd; 03-22-2011 at 01:59 AM.
|
|
|
03-22-2011, 04:00 AM
|
#14
|
|
Master Plumber
Join Date: Aug 2007
Location: In your attic.
Posts: 8,107
|
Quote:
Originally Posted by Rockyd
Edit - We have to pull ground wire everywhere in pipe in Anchorage, we go "over the top" on that end. Then again our ground moves a lot up here because of frost, earthquakes, etc. so it's not such a bad thing.
|
I do that same practice as well, even though it isnt mandatory.
~Matt
__________________
Poor planning on your part does not constitute an emergency on my part.
Advertising space available. Inquire within.
|
|
|
03-23-2011, 08:54 AM
|
#15
|
|
PES
Join Date: Feb 2011
Location: NY
Posts: 1,350
|
It's an interesting conversation but no matter how you slice it, the gas pipe will always be bonded. Done intentionally or not.
Sent from my iPhone using ET Forum
__________________
Sal
P.E.S
|
|
|
04-05-2011, 10:57 AM
|
#16
|
|
Resi Service Electrician
Join Date: Sep 2008
Location: California
Posts: 1,257
|
Sacramento is actually pretty cool to work with. We get direct numbers to inspectors, which was unheard of in the bay area unless we were in really good with one inparticular, they post them right on the website, how cool is that.
The local utility (SMUD) is easy to deal with too; the guy who came out for the dnr for my underground service said. "I can just tape up the wires real good.. that okay with you?" Like heck yah dude that's cool! And he left the meter. So after I was done customer immediately had power and they could take their time coming back to seal up the meter.
In the bay area I always did my own dnr's (even though sometimes they would make a stink about it) because the utility woudn't always be as easy to deal with at times. Glad to see things are pretty close to the same requirements with a little more catering to us electricians...finally!
__________________
"Understand one thing every one has a place in this trade, and no matter what your skill set I doubt you know it all." brian john
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Linear Mode
|
Posting Rules
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|