Spot the violation(s)

2K views 18 replies 10 participants last post by  Shockdoc 
#1 · (Edited)
I recently did an overhead to underground service changeover (meter base and grounding only).

Here is the existing meter base with cold water bond below:






Notice anything?
 
See less See more
2
#9 ·
MiGB around here exiting the meter pan in metal, does the ground sneak up behind the meter pan and in with the nipple somewhere? I can't see anyone faking a piece of conduit for a ground.
 
#12 ·
I'm guessing this had been upgraded before and whoever did it just cut the water bond (conduit) off and set the can on top of it.

In the 50's, here, the standard method was to run a #8 in rigid conduit and attach both to the water pipe with a specifically designed clamp that would take the conduit as well as the wire.
 