Discussion Starter · #1 ·
Now that I delivers hot juice to the 75 hp motor through 300 mcm
The box on the motor is too small to accomodate all those in-coming wires

I want quit and go back to my hometown
 

·
Registered
Joined
·
1,622 Posts
You will need to replace the motor peckerhead with a "Hoffman" type box appropriate for the environment. This is a common field mod for large motor feeders or parallel runs. Some motors can be ordered with oversized peckerheads, but lead time and cost usually rule out this option unless it is a specification controlled project.

I would think that this motor would be a good choice to use a parralelled feeder. (Two runs of 1 1/4 with (3) 1/0 each)
 

·
Electrical Contractor
Joined
·
9,325 Posts
Now that I delivers hot juice to the 75 hp motor through 300 mcm
The box on the motor is too small to accomodate all those in-coming wires

I want quit and go back to my hometown
You have my permission, go!! Marvin K. Tamas, you must go now!!!:laughing:
 