Bidding on a 64x40 pole building..
-Trench 170' to customers pole and install 4/0 URD in 2 1/2 pvc, U-guard up the pole, mini ex rental is 200 a day and backfill
-Install 200 AMP SQD disconnect on outside
-Install 200 amp QO 30/40 panel
-Run 10/2 100 feet for Air Compressor Circuit
-10 Outlets mounted on beams ( run Emt to ceiling than with 12-2 romex
-Install 8 T5 6 lamp fixtures (customer supplying)
-Install (3) 100 Watt MH wallpacks
-NO water, so installing 2 ground rods
-Run 6-2 115' for welder circuit
-The building is attached to the old shop so im running 100 amp SER to to power the old building (Roughly 85')
Supply all materials except lights.
-Trench 170' to customers pole and install 4/0 URD in 2 1/2 pvc, U-guard up the pole, mini ex rental is 200 a day and backfill
-Install 200 AMP SQD disconnect on outside
-Install 200 amp QO 30/40 panel
-Run 10/2 100 feet for Air Compressor Circuit
-10 Outlets mounted on beams ( run Emt to ceiling than with 12-2 romex
-Install 8 T5 6 lamp fixtures (customer supplying)
-Install (3) 100 Watt MH wallpacks
-NO water, so installing 2 ground rods
-Run 6-2 115' for welder circuit
-The building is attached to the old shop so im running 100 amp SER to to power the old building (Roughly 85')
Supply all materials except lights.