So the shell of this building was built before we stepped foot on the job. GC ran transformer and generator pipes. There is no building steel wire though. Anyone had this happen to them before?
Any ideas?
Any ideas?
Do you have any reference that is legal? There is already a triangular ground rod system requested, will this suffice?Here, we would simply have to install ground rods in lieu of the ufer, but I have read of areas/inspectors that would require the GEC to go to any new rebar/footings.