I'm designing the physical layout for running present and future circuits to assigned parking spots in a common garage for use with Electrical Vehicle (EV) charging stations. All will be 240 VAC. This is for a multi-unit dwelling in San Francisco, CA. with 25 parking spaces on two floors adjacent to the meters. Circuits and charging stations will be added incrementally as people purchase their EVs. The objective is to lower each unit's cost by establishing the common raceways to minimize the incremental labor and materials for each run. Additionally, the design should allow for each unit's owner to decide what service/product they would rather install instead of establishing a standard for the entire building. At the moment only one resident has the need for a charging station.
Option 1) One solution would be to run a single 4" conduit from the junction (near the bank of meters) so that each circuit could be pulled when required. One or more conduits would be run between the meter bank and the junction (about 5 ft). This is desirable because a concrete floor and wall lie between the meters and the parking garage. I suspect that combining separately-metered conductors into a single conduit violates code.
Option 2) Alternatively we install meters at each parking spot and extend the service drop/lateral into a junction in the middle of the garages' ceilings. Each parking spot would install a separate meter that taps into it. I suspect that arrangement exposes too much un-metered raceway to unauthorized taps. Inspectors would probably be uneasy with that arrangement.
Option 3) Finally, because the cost would be primarily in drilling through walls, a fire-rated pass-through could be installed and each conduit would be routed through it when required. This opens up a big hole into the floor and wall. Structurally it is undesirable and it would probably be expensive.
Option 4) The fall-back is to install each circuit incrementally and ultimately drill 50 (25 X 2) holes and run individual conduits to each parking spot.
Any guidance is appreciated.
Option 1) One solution would be to run a single 4" conduit from the junction (near the bank of meters) so that each circuit could be pulled when required. One or more conduits would be run between the meter bank and the junction (about 5 ft). This is desirable because a concrete floor and wall lie between the meters and the parking garage. I suspect that combining separately-metered conductors into a single conduit violates code.
Option 2) Alternatively we install meters at each parking spot and extend the service drop/lateral into a junction in the middle of the garages' ceilings. Each parking spot would install a separate meter that taps into it. I suspect that arrangement exposes too much un-metered raceway to unauthorized taps. Inspectors would probably be uneasy with that arrangement.
Option 3) Finally, because the cost would be primarily in drilling through walls, a fire-rated pass-through could be installed and each conduit would be routed through it when required. This opens up a big hole into the floor and wall. Structurally it is undesirable and it would probably be expensive.
Option 4) The fall-back is to install each circuit incrementally and ultimately drill 50 (25 X 2) holes and run individual conduits to each parking spot.
Any guidance is appreciated.