Hello, I am from the UK and I was wondering what you americans call First Fix Electrics and Second Fix Electrics.

First Fix: Positioning and securing of accessory boxes


Second Fix: Preparation and positioning of cables


Thanks in advanced
 

·
Administrator
Retired EC
Joined
·
23,139 Posts
Never heard the terms..but welcome to the forum.
 

·
Premium Member
Joined
·
20,983 Posts
We do both of those steps at once, and call it the "rough-in", "rough wiring", or simply the "rough".
 

·
evil bastard
Joined
·
15,771 Posts
MDShunk said:
We do both of those steps at once, and call it the "rough-in", "rough wiring", or simply the "rough".
Around here, it's two different terms. I call his first description " roughing in"

Then come back "cut in" all the cables. Its done in two different steps.

Rough the whole house in will get all the cables in place, but just hanging at each box.

Cutting in gets all those wires into the boxes and grounds made up.
 

·
Registered
Joined
·
12,376 Posts
Around here, it's two different terms. I call his first description " roughing in"

Then come back "cut in" all the cables. Its done in two different steps.

Rough the whole house in will get all the cables in place, but just hanging at each box.

Cutting in gets all those wires into the boxes and grounds made up.
Pigtails and grounds must be made up ready for devices to get a rough in here.
 