Is anyone using any specific software or program for manpower scheduling/tracking?

currently using excel spreadsheets and some are using projects. But more often than not end up with at least one pissing match a week about sharing guys or trying to arrange allocations.

Thanks
 

· RIP 1959-2015
Joined
·
39,532 Posts
Is anyone using any specific software or program for manpower scheduling/tracking?

currently using excel spreadsheets and some are using projects. But more often than not end up with at least one pissing match a week about sharing guys or trying to arrange allocations.

Thanks
That always happens it seems..:laughing:
 

· Registered
Joined
·
216 Posts
ms project is pretty efficient at resource scheduling. There are some new views in the newer versions that show you your resources on a timeline, identifies conflicts, etc. Then you can just drag jobs around until it makes sense.

Still, no matter how much you plan, reality will never follow your plan. A common misconception is that this means you shouldn't plan. The planning process is essential even if the plan is not followed.
 

· Registered
Joined
·
591 Posts
Discussion Starter · #5 ·
we use an older version of Projects. I don't know how well it would work for multiple jobs. may try and play with it.

Trying to use Microsoft outlook at the moment, but gets really cluttered after you get a few open.

I know there are loads of programs out there, just didn't know if anyone had any experience using any of them.
 

· Registered
Joined
·
216 Posts
I encourage you yo try the newest ms project 2013. You setup a "master project", put in your resources (including work hours, lunch breaks, stat holidays, etc), then make it into a shared resource pool. Then you setup your other projects (jobs) to use that resource pool. It will help you move your jobs around into the most efficient order.

I use it when I have too much work coming up to fit into my brain. It really helps make the right scheduling decisions. All of my projects require a rough in and finish stage, and usually have low and high voltage components. Most of my guys are strong in one or two areas. You can program in their skills and project uses that data to propose a schedule. Its just a starting point, you make adjustments as you see fit. Then it can print out or email group schedules, individual agendas, time cards, whatever you like. Better yet you can sync it up with their calendars on their smart phones.
 

· Registered
Joined
·
591 Posts
Discussion Starter · #8 ·
vinister said:
I encourage you yo try the newest ms project 2013. You setup a "master project", put in your resources (including work hours, lunch breaks, stat holidays, etc), then make it into a shared resource pool. Then you setup your other projects (jobs) to use that resource pool. It will help you move your jobs around into the most efficient order. I use it when I have too much work coming up to fit into my brain. It really helps make the right scheduling decisions. All of my projects require a rough in and finish stage, and usually have low and high voltage components. Most of my guys are strong in one or two areas. You can program in their skills and project uses that data to propose a schedule. Its just a starting point, you make adjustments as you see fit. Then it can print out or email group schedules, individual agendas, time cards, whatever you like. Better yet you can sync it up with their calendars on their smart phones.

Cheers.

I'll have a look!
 