Nice job
Times two....:thumbup:Looks good. :thumbsup:More pics please. What type of building?
Yup. It's pretty safe to assume if the terminations look neat and pretty then they've probably all been cut to fitDeep Cover said:It looks great, which leads me to ask how close are the lengths of wire?
I'm guessing 7000meadow said:I could never do that. Looks nice:thumbup: What is the service rated?
I don't understand exactly what you are asking, but from the service, about 50 feet. To the indoor gear it's about 200 feet. There were actually 2 more cabinets in this gear 2 incoming from 2 service transformers. and two out to indoor gear I will try to find pics of the emergency gear from generators.It looks great, which leads me to ask how close are the lengths of wire?
It is a 7000 a serviceI could never do that. Looks nice:thumbup:
What is the service rated?
Shoot I bet with 11 conduits they could be as much as 6-8' between the first and lastDeep Cover said:Within how many feet are the individual parallel runs of each other? Obviously they are not exactly the same.
Yes all cut to fit. The first one took a day and a half. The other 3 i finished in a day a piece.Yup. It's pretty safe to assume if the terminations look neat and pretty then they've probably all been cut to fit
For a 50' run that could be anywhere between 12-16%. That wouldn't be acceptable in my mind and there is really no way an inspector could catch it.Shoot I bet with 11 conduits they could be as much as 6-8' between the first and last
Exactly. This is another reason we don't do services over 3000 amps, it's just not practical. Our poco lets us feed our buildings with multiple services as long as they're at least 300' apart so we go that route or run medium voltageDeep Cover said:For a 50' run that could be anywhere between 12-16%. That wouldn't be acceptable in my mind and there is really no way an inspector could catch it.