Here is a load letter I used..

August 25, 2008

LIPA
1650 Brentwood Road
Brentwood, N.Y. 11717

REF. # T100744526


NEW BUILDING #1 - Six (6) 200 amp. Single Phase Services with 600 amp. Disconnect Switch - TOTAL LOAD 25KW.

NEW BUILDING #2 - Ten (10) 100 amp. Single Phase Services with 600 amp. Disconnect Switch - TOTAL LOAD 25KW.

EXISTING BUILDING #3 - Eleven (11) 100 amp. Single Phase Services with 600 amp. Disconnect Switch - TOTAL LOAD 25KW.

EXISTING BUILDING #4 - Eleven (11) 100 amp. Single Phase services with 600 amp Disconnect Switch - TOTAL LOAD 25KW
 

·
Scotchkote Installer
Joined
·
30,665 Posts
I figured it was the letter from a GC saying that you were the only one that bid but you are too high. That's a load letter.
It is telling the PoCo what the new load will be on existing lines and transformers.. so they can upgrade if need be..
 