I am a project manager for a commercial build out and need help verifying information provided by the general contractor. We are building a data center into the space and need 19 each - 120v/20a and 3 each - 240/30a 1 phase. The space currently has 200 Amp electrical service. Will we need to upgrade to 300 Amps to meet the additional data center needs?
 