Stopped by a job site today and the first thing I saw when I pulled in was a new 4" pvc conduit with a new pvc box and new pulled conductors. Gee I wonder why they didn't finish ?
 

· Premium Member
Joined
·
20,945 Posts
When I see that, on a house, it makes me wonder what sort of abomination they made out of the conduit run that required another pull point.
 
  • Like
Reactions: MTW

· Professional Nit Picker
Joined
·
2,378 Posts
Discussion Starter · #8 · (Edited)
It's 2x4 mounted to the building.

This is a community maintenance type building. The new PVC it being run to a pool house that is undergoing a complete gut and redo. There was a major problem with the original feed to the building that required a new feeder to be run. The pVC out of the bottom of the box goes underground to the pool house building. They needed to install a pull point due to the number of bends
 

· Homer to Jebus
Electron Flow Consultant
Joined
·
875 Posts
Slap an expansion coupling on it and a cover. Job done, check cashed. :laughing::whistling2:
 

· Professional Nit Picker
Joined
·
2,378 Posts
Discussion Starter · #18 · (Edited)
What's the yellow tag in the box say?
Thats a tag I left for the contractor to call me, as he was not on site. I also put in a telephone call to him. When he called back I discussed it with him and it will be changed to a properly sized box.

( yellow tag in question is in another photo in my photobucket account, that has been locked now)
 
1 - 20 of 36 Posts
This is an older thread, you may not receive a response, and could be reviving an old thread. Please consider creating a new thread.
Top