Just estimated a job for some recessed led light to be installed 24 to be exact for a commercial project. 9 are getting replaced with new ones, 16 fluorescent lights are getting demoed out completely and there is attic space and I gave the guy a price of 4200$ Labor and material and 5000 $ with the lights included that's with the one guy I bringing in on the job as well is that a fair price I say it's gonna take me 2 days to so it maybe 2 1/2
 

·
Rest In Peace
Joined
·
6,298 Posts
Just estimated a job for some recessed led light to be installed 24 to be exact for a commercial project. 9 are getting replaced with new ones, 16 fluorescent lights are getting demoed out completely and there is attic space and I gave the guy a price of 4200$ Labor and material and 5000 $ with the lights included that's with the one guy I bringing in on the job as well is that a fair price I say it's gonna take me 2 days to so it maybe 2 1/2
What was the question?
 

·
Registered
Joined
·
45 Posts
Discussion Starter · #8 ·
I estimated 3 dayz 24hrs 135 hr for 2 guys $3240.00 material 12/2 3 rolls at $225 my permit charge of $375 connectors ground screws 50$ recessed light 30 per light 25 total 750$ I didn't even add in bulbs or trim or put a extra 15% on. The total or add in my gas expense so this is the total 4640$
 

·
Registered
Joined
·
3,345 Posts
So you have 40/hrs direct labor @construction rate burdened or 20hrs/20hrs MR-HR?...or do you calculate all hrs same????OH at 30%??? materials at x1.5? x1.6?......:blink:
 

·
Registered
Joined
·
45 Posts
Discussion Starter · #10 ·
Moopiehead said:
I estimated 3 dayz 24hrs 135 hr for 2 guys $3240.00 material 12/2 3 rolls at $225 my permit charge of $375 connectors ground screws 50$ recessed light 30 per light 25 total 750$ I didn't even add in bulbs or trim or put a extra 15% on the total or add in my gas expense and this what I came up with is that reasonable
 

·
Registered
Joined
·
45 Posts
Discussion Starter · #11 ·
Moopiehead said:
I estimated 3 dayz 24hrs 135 hr for 2 guys $3240.00 material 12/2 3 rolls at $225 my permit charge of $375 connectors ground screws 50$ recessed light 30 per light 25 total 750$ I didn't even add in bulbs or trim or put a extra 15% on. The total or add in my gas expense so this is the total 4640$ Is this reasonable
 

·
Registered
Joined
·
45 Posts
Discussion Starter · #17 ·
RGH said:
So you have 40/hrs direct labor @construction rate burdened or 20hrs/20hrs MR-HR?...or do you calculate all hrs same????OH at 30%??? materials at x1.5? x1.6?......:blink:
no direct labor I just estimated I'll be there no more then 3 dayz 8 hrs per day me in my other guy 15 fluorescent are getting took out the ceiling as well as putting up 24 new cans and it's Sheetrock ceiling but it does have attic space
 